20 U.S.C. § 76mPhotovoltaic system

submitted 18 years ago by Pub. L. 85-874 to r/title-20-EDUCATION · 84 words · no verdicts yet

in plain englishAI-generated · not legal advice

The Kennedy Center's Board may study, design, and build a solar (photovoltaic) power system on the Center's main roof. Before starting construction, the Board must report on the project's feasibility and design to two congressional committees at least 60 days ahead of time.

(a) In general: The Board may study, plan, design, engineer, and construct a photovoltaic (solar power) system for the main roof of the Kennedy Center. (b) Report: At least 60 days before construction begins, the Board must send a report on the project's feasibility and design to the House Committee on Transportation and Infrastructure and the Senate Committee on Environment and Public Works.
the actual law source: uscode.house.gov ↗public domain
(a) In general

The Board may study, plan, design, engineer, and construct a photovoltaic system for the main roof of the John F. Kennedy Center for the Performing Arts.

(b) Report

Not later than 60 days before beginning construction of the photovoltaic system pursuant to subsection (a), the Board shall submit to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Environment and Public Works of the Senate a report on the feasibility and design of the project.

Source credit: (Pub. L. 85–874, § 7, as added, Pub. L. 110–338, § 3, Oct. 3, 2008, 122 Stat. 3731.)

history & why it existsrecord from the source credit
  • 2008Enacted · Pub. L. 85-874 · 122 Stat. 3731

A history note hasn’t been published yet. The record shows enactment by Pub. L. 85-874 on 2008-10-03.

all 0 arguments · sorted by: best

0/280

no arguments yet — make the first case