22 U.S.C. § 306Contracting methods in capital construction

submitted 5 years ago by Pub. L. 117-81 to r/title-22-FOREIGN-RELATIONS-AND-INTERCOURSE · 186 words · no verdicts yet

in plain englishAI-generated · not legal advice

The Secretary of State must use the 'design-build' method to build new U.S. diplomatic posts. The Secretary can skip it only by telling Congress why. The Secretary must also report to Congress on how construction performance is measured.

(a) Delivery. The Secretary of State must use the "design-build" method -- one contractor handles both design and construction -- for new U.S. diplomatic posts that had not yet gotten design or construction contracts as of December 27, 2021. The Secretary can skip this only by telling the right congressional committees that design-build would not work. (b) Notification. Before using a different contracting method, the Secretary must tell those committees in writing and explain why. This notice can be part of another report about the new post. (c) Performance evaluation. Within 180 days of December 27, 2021, the Secretary must report to Congress on how it will measure performance -- following the GAO's "Standards for Internal Control in the Federal Government" -- for design, construction, lifecycle cost, and building maintenance work done by the Bureau of Overseas Building Operations.
the actual law source: uscode.house.gov ↗public domain
(a) Delivery

Unless the Secretary of State notifies the appropriate congressional committees that the use of the design-build project delivery method would not be appropriate, the Secretary shall make use of such method at United States diplomatic posts that have not yet received design or capital construction contracts as of December 27, 2021.

(b) Notification

Before executing a contract for a delivery method other than design-build in accordance with subsection (a), the Secretary of State shall notify the appropriate congressional committees in writing of the decision, including the reasons therefor. The notification required by this subsection may be included in any other report regarding a new United States diplomatic post that is required to be submitted to the appropriate congressional committees.

(c) Performance evaluation

Not later than 180 days after December 27, 2021, the Secretary of State shall report to the appropriate congressional committees regarding performance evaluation measures in accordance with GAO’s “Standards for Internal Control in the Federal Government” that will be applicable to design and construction, lifecycle cost, and building maintenance programs of the Bureau of Overseas Building Operations of the Department.

Source credit: (Pub. L. 117–81, div. E, title LII, § 5211, Dec. 27, 2021, 135 Stat. 2358.)

history & why it existsrecord from the source credit
  • 2021Enacted · Pub. L. 117-81 · 135 Stat. 2358

A history note hasn’t been published yet. The record shows enactment by Pub. L. 117-81 on 2021-12-27.