41 U.S.C. § 7104 — Contractor’s right of appeal from decision by contracting officer

submitted 15 years ago by Pub. L. 111-350 to r/title-41-PUBLIC-CONTRACTS · 230 words · no verdicts yet

in plain englishAI-generated · not legal advice

This section gives a contractor two routes to challenge a contracting officer’s decision: appeal to an agency board within 90 days or, subject to the stated exception for the Tennessee Valley Authority, sue directly in the specified federal court within 12 months.

(a) Appeal to Agency Board .— A contractor, within 90 days from the date of receipt of a contracting officer’s decision under section 7103 of this title , may appeal the decision to an agency board as provided in section 7105 of this title .
(b) Bringing an Action De Novo in Federal Court.—
(1) General rule .— Except as provided in paragraph (2), and in lieu of appealing the decision of a contracting officer under section 7103 of this title to an agency board, a contractor may bring an action directly on the claim in the United States Court of Federal Claims, even if any contract provision, regulation, or rule of law to the contrary.
(2) Tennessee valley authority .— In the case of an action against the Tennessee Valley Authority, the contractor may only bring an action directly on the claim in a district court of the United States under section 1337 of title 28 , even if any contract provision, regulation, or rule of law to the contrary.
(3) Time for filing .— A contractor must file any action under paragraph
(1) or
(2) within 12 months from the date of receipt of a contracting officer’s decision under section 7103 of this title .
(4) De novo .— An action under paragraph
(1) or
(2) must proceed anew under the rules of the appropriate court.

the actual law source: uscode.house.gov ↗public domain
(a)Appeal to Agency Board.—

A contractor, within 90 days from the date of receipt of a contracting officer’s decision under section 7103 of this title, may appeal the decision to an agency board as provided in section 7105 of this title.

(b)Bringing an Action De Novo in Federal Court.—
(1)In general.—

Except as provided in paragraph (2), and in lieu of appealing the decision of a contracting officer under section 7103 of this title to an agency board, a contractor may bring an action directly on the claim in the United States Court of Federal Claims, notwithstanding any contract provision, regulation, or rule of law to the contrary.

(2)Tennessee valley authority.—

In the case of an action against the Tennessee Valley Authority, the contractor may only bring an action directly on the claim in a district court of the United States pursuant to section 1337 of title 28, notwithstanding any contract provision, regulation, or rule of law to the contrary.

(3)Time for filing.—

A contractor shall file any action under paragraph (1) or (2) within 12 months from the date of receipt of a contracting officer’s decision under section 7103 of this title.

(4)De novo.—

An action under paragraph (1) or (2) shall proceed de novo in accordance with the rules of the appropriate court.

Source credit: (Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3820.)

history & why it existsrecord from the source credit
  • 2011Enacted · Pub. L. 111-350 · 124 Stat. 3820

A history note hasn’t been published yet. The record shows enactment by Pub. L. 111-350 on 2011-01-04.

all 0 arguments · sorted by: best

0/280

no arguments yet — make the first case