This law spells out what a reclamation project proposal must include. It needs cost estimates, state review, and a fair split of costs among project purposes. It also covers local funding shares, congressional review, and control of the finished project.

(a) Plans and estimates; review by States; allocation of capital costs If a project has never been authorized for construction before, its proposal must include a detailed plan and cost estimate. This must be as complete as the reports normally required before a federal reclamation project is authorized. The states in the project's river basin must get to review the proposal, the same way section 701–1(c) of title 33 requires. If the proposal is only for rehabilitating and improving an already-existing project, this review can be limited to the state or states where the project sits. The proposal must also propose how to divide the project's capital costs among its purposes. Costs for a facility used for only one purpose go entirely to that purpose. Costs for a facility shared by several purposes must be divided fairly, so each purpose pays its share of the shared cost. The cost of preventing harm to fish and wildlife counts as a project cost too, split among the relevant purposes. (b) Lands and water rights; ownership; financing (1) The proposal must show that the organization already has, or can get, all the land and water rights the project needs to be built, run, and maintained. Federal land already under the Secretary's control does not count here. The proposal must also show the organization is ready and able to pay — using money other than a federal loan or grant — its share of the project's cost, including the cost of getting land and water rights. An exception applies under section 422e(b)(2). The Secretary decides what counts as proper here. (2) The Secretary must require the organization to pay at least 25 percent of the project's allowable estimated cost, using non-federal money. The Secretary can lower this share, but never below 10 percent, if the organization truly cannot get financing elsewhere on reasonable terms. Any project sent to Congress must include letters from lenders, or similar proof, showing the organization could not get that financing. When counting how much the organization has already contributed, the Secretary credits the cost of studies, surveys, engineering, and similar prep work; the cost of land and rights-of-way for the project; and the $5,000 fee paid under section 422c. Grants given under section 422e(b) do not count toward the project's allowable estimated cost. (c) Transmittal of findings and approval to Congress; certification of soil survey; reservation of land Once the Secretary and the state's Governor (or an agency the Governor picks) find a project financially workable, the Secretary decides it is a reasonable risk under this subchapter, and the Secretary approves it, those findings go to Congress. Every project proposal sent to Congress must certify that a proper soil survey and land classification was done — or that the land has already proven it can grow crops successfully under irrigation. The proposal must also include a study of soil traits that might cause toxic or harmful irrigation runoff. When submitting the proposal, or when deciding it is a reasonable risk, the Secretary can set aside federal land under their control that the project needs. This reservation of land expires after two years unless a contract is signed under section 422e. (d) Amount of loan and/or grant; increase by Secretary At the time of submitting the proposal to Congress, or any time before construction finishes — including for already-approved projects — the Secretary can increase the requested loan or grant. This can only go up to the maximum allowed under section 422e(a). The purpose is to cover construction costs that have risen due to price increases. (e) Appropriation; nonapplicability Congress cannot appropriate money for a project until sixty calendar days pass. This clock starts when the Secretary's findings and approval reach Congress. Days when either the House or the Senate is out of session for more than three days in a row do not count toward the sixty. Even after sixty days, funding is blocked if the House Natural Resources Committee or the Senate Energy and Natural Resources Committee formally disapproves the project. This subsection does not apply to proposals made under section 422f. (f) Consideration of financial feasibility, emergency, or urgent need; jurisdiction and control of project works The Secretary must properly weigh the project's financial feasibility and any emergency or urgent need for it. Once built, every project facility stays under the control of the local organization that contracted for it — subject to the terms of its repayment contract.
the actual law source: uscode.house.gov ↗public domain
(a) Plans and estimates; review by States; allocation of capital costs

Any proposal with respect to the construction of a project which has not theretofore been authorized for construction under the Federal reclamation laws shall set forth, among other things, a plan and estimated cost in detail comparable to those included in preauthorization reports required for a Federal reclamation project; shall have been submitted for review by the States of the drainage basin in which the project is located in like manner as provided in section 701–1(c) of title 33, except that the review may be limited to the State or States in which the project is located if the proposal is one solely for rehabilitation and betterment of an existing project; and shall include a proposed allocation of capital costs to functions such that costs for facilities used for a single purpose shall be allocated to that purpose and costs for facilities used for more than one purpose shall be so allocated among the purposes served that each purpose will share equitably in the costs of such joint facilities. The costs of means and measures to prevent loss of and damage to fish and wildlife resources shall be considered as project costs and allocated as may be appropriate among project functions.

(b) Lands and water rights; ownership; financing
(1)

Every such proposal shall include a showing that the organization already holds or can acquire all lands and interests in land (except public and other lands and interests in land owned by the United States which are within the administrative jurisdiction of the Secretary and subject to disposition by him) and rights, pursuant to applicable State law, to the use of water necessary for the successful construction, operation, and maintenance of the project and that it is ready, able, and willing to finance otherwise than by loan and grant of Federal funds such portion of the cost of the project (which portion shall include all costs of acquiring lands, interests in land, and rights to the use of water), except as provided in section 422e(b)(2) of this title as the Secretary shall have advised is proper in the circumstances.

(2)

The Secretary shall require each organization to contribute toward the cost of the project (other than by loan and/or grant of Federal funds) an amount equal to 25 percent or more of the allowable estimated cost of the project: Provided, That the Secretary, at his discretion, may reduce the amount of such contribution to the extent that he determines that the organization is unable to secure financing from other sources under reasonable terms and conditions, and shall include letters from lenders or other written evidence in support of any funding of an applicant’s inability to secure such financing in any project proposal transmitted to the Congress: Provided further, That under no circumstances shall the Secretary reduce the amount of such contribution to less than 10 percent of the allowable estimated total project costs. In determining the amount of the contribution as required by this paragraph, the Secretary shall credit toward that amount the cost of investigations, surveys, engineering, and other services necessary to the preparation of proposals and plans for the project as required by the Secretary, and the costs of lands and rights-of-way required for the project, and the $5,000 fee described in section 422c of this title. In determining the allowable estimated cost of the project, the Secretary shall not include the amount of grants accorded to the organization under section 422e(b) of this title.

(c) Transmittal of findings and approval to Congress; certification of soil survey; reservation of land

At such time as a project is found by the Secretary and the Governor of the State in which it is located (or an appropriate State agency designated by him) to be financially feasible, is determined by the Secretary to constitute a reasonable risk under the provisions of this subchapter, and is approved by the Secretary, such findings and approval shall be transmitted to the Congress. Each project proposal transmitted by the Secretary to the Congress shall include a certification by the Secretary that an adequate soil survey and land classification has been made, or that the successful irrigability of those lands and their susceptibility to sustained production of agricultural crops by means of irrigation has been demonstrated in practice. Such proposal shall also include an investigation of soil characteristics which might result in toxic or hazardous irrigation return flows. The Secretary, at the time of submitting the project proposal to Congress or at the time of his determination that the requested project constitutes a reasonable risk under the provisions of this subchapter, may reserve from use or disposition inimical to the project any lands and interests in land owned by the United States which are within his administrative jurisdiction and subject to disposition by him and which are required for use by the project. Any such reservation shall expire at the end of two years unless the contract provided for in section 422e of this title shall have been executed.

(d) Amount of loan and/or grant; increase by Secretary

At the time of his submitting the project proposal to the Congress, or at any subsequent time prior to completion of construction of the project, including projects heretofore approved, the Secretary may increase the amount of the requested loan and/or grant to an amount within the maximum allowed by section 422e(a) of this title, as amended by Pub. L. 94–181, to compensate for increases in construction costs due to price escalation.

(e) Appropriation; nonapplicability

No appropriation shall be made for financial participation in any such project prior to sixty calendar days (which sixty days, however, shall not include days on which either the House of Representatives or the Senate is not in session because of an adjournment of more than three calendar days to a day certain) from the date on which the Secretary’s findings and approval are submitted to the Congress and then only if, within said sixty days, neither the Committee on Natural Resources of the House of Representatives nor the Committee on Energy and Natural Resources of the Senate disapproves the project proposal by committee resolution. The provisions of this subsection (e) shall not be applicable to proposals made under section 422f of this title.

(f) Consideration of financial feasibility, emergency, or urgent need; jurisdiction and control of project works and facilities

The Secretary shall give due consideration to financial feasibility, emergency, or urgent need for the project. All project works and facilities constructed under this subchapter shall remain under the jurisdiction and control of the local contracting organization subject to the terms of the repayment contract.

Source credit: (Aug. 6, 1956, ch. 972, § 4, 70 Stat. 1044; Pub. L. 85–47, § 1(a), (b), June 5, 1957, 71 Stat. 48; Pub. L. 89–553, § 1(2), (3), Sept. 2, 1966, 80 Stat. 376; Pub. L. 92–167, § 1(2), Nov. 24, 1971, 85 Stat. 488; Pub. L. 94–181, § 1(c)–(e), Dec. 27, 1975, 89 Stat. 1049, 1050; Pub. L. 99–546, title III, §§ 304, 305, Oct. 27, 1986, 100 Stat. 3053, 3054; Pub. L. 103–437, § 16(b), Nov. 2, 1994, 108 Stat. 4594.)

history & why it existsrecord from the source credit
  • 1956Enacted · Act of Aug. 6, 1956, ch. 972 · 70 Stat. 1044
  • 1957Amended · Pub. L. 85-47 · 71 Stat. 48
  • 1966Amended · Pub. L. 89-553 · 80 Stat. 376
  • 1971Amended · Pub. L. 92-167 · 85 Stat. 488
  • 1975Amended · Pub. L. 94-181 · 89 Stat. 1049, 1050
  • 1986Amended · Pub. L. 99-546 · 100 Stat. 3053, 3054
  • 1994Amended · Pub. L. 103-437 · 108 Stat. 4594

A history note hasn’t been published yet. The record shows enactment by ch. 972 on 1956-08-06.