43 U.S.C. § 478 — Pecuniary penalty for nonpayment of installments of construction charges
submitted 112 years ago by ch. 247 to r/title-43-PUBLIC-LANDS · 109 words · no verdicts yet
If a water-right applicant or entryman failed to pay a construction-charge installment on time before December 5, 1924, a 1 percent penalty is added to the unpaid amount. Another 1 percent penalty is added for the amount still unpaid on the first of each following month. For installments due after December 5, 1924, this monthly penalty is cut in half, to one-half of 1 percent.
If any water-right applicant or entryman shall have, prior to December 5, 1924, failed to pay any installment of his construction charges when due, there shall be added to the amount unpaid a penalty of 1 per centum thereof, and there shall be added a like penalty of 1 per centum of the amount unpaid on the first day of each month thereafter so long as such default shall have continued: Provided, That the penalty of 1 per centum per month against delinquent accounts, is reduced to one-half of 1 per centum per month, as to all installments which may become due after December 5, 1924.
Source credit: (Aug. 13, 1914, ch. 247, § 3, 38 Stat. 687; Dec. 5, 1924, ch. 4, § 4, subsec. H, 43 Stat. 703.)
- 1914Enacted · Act of Aug. 13, 1914, ch. 247 · 38 Stat. 687
- 1924Amended · Act of Dec. 5, 1924, ch. 4 · 43 Stat. 703