49 U.S.C. § 22903Project management oversight

submitted 18 years ago by Pub. L. 110-432 to r/title-49-TRANSPORTATION · 279 words · no verdicts yet

in plain englishAI-generated · not legal advice

To get federal money for a major capital project, an applicant must have a Secretary-approved project management plan. That plan must cover staffing, budgets, schedules, and quality control, among other things. Recipients must also give the Secretary access to construction sites and records when reasonably needed.

(a) Project Management Plan Requirements. To get federal financial help for a major capital project under this chapter, an applicant must write and carry out a project management plan that the Secretary of Transportation approves. That plan must cover twelve things: (1) enough recipient staff, with clear reporting lines, job responsibilities, job descriptions, and qualifications; (2) a budget covering the project management team, consultants, buying property, moving utilities, testing staff, audits, and other costs the recipient can justify; (3) a construction schedule; (4) a system for controlling documents and keeping records; (5) a documented, organized way of handling construction change orders; (6) the organizational structure, management skills, and staffing needed throughout construction; (7) quality control and quality assurance steps for construction, installing systems, and fitting components together; (8) policies and procedures for testing materials; (9) internal rules for carrying out and reporting on the plan; (10) rules and procedures for testing the finished system or its major parts; (11) regular updates to the plan, especially about budget, schedule, financing, and expected ridership; and (12) a promise from the recipient to regularly send the Secretary its project budget and schedule. (b) Repealed. This subsection was repealed by a 2015 law (Public Law 114–94). (c) Access to Sites and Records. Every recipient of assistance under this chapter must give the Secretary, and any contractor the Secretary hires, access to its construction sites and records whenever that access is reasonably necessary.
the actual law source: uscode.house.gov ↗public domain
(a)Project Management Plan Requirements.—

To receive Federal financial assistance for a major capital project under this chapter, an applicant must prepare and carry out a project management plan approved by the Secretary of Transportation. The plan shall provide for—

(1)

adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;

(2)

a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;

(3)

a construction schedule for the project;

(4)

a document control procedure and recordkeeping system;

(5)

a change order procedure that includes a documented, systematic approach to handling the construction change orders;

(6)

organizational structures, management skills, and staffing levels required throughout the construction phase;

(7)

quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;

(8)

material testing policies and procedures;

(9)

internal plan implementation and reporting requirements;

(10)

criteria and procedures to be used for testing the operational system or its major components;

(11)

periodic updates of the plan, especially related to project budget and project schedule, financing, and ridership estimates; and

(12)

the recipient’s commitment to submit periodically a project budget and project schedule to the Secretary.

[(b)

Repealed. Pub. L. 114–94, div. A, title XI, § 11316(p), Dec. 4, 2015, 129 Stat. 1679]

(c)Access to Sites and Records.—

Each recipient of assistance under this chapter shall provide the Secretary and a contractor the Secretary chooses under subsection (b) of this section with access to the construction sites and records of the recipient when reasonably necessary.

Source credit: (Added Pub. L. 110–432, div. B, title III, § 301(a), Oct. 16, 2008, 122 Stat. 4941, § 24403; amended Pub. L. 114–94, div. A, title XI, § 11316(p), Dec. 4, 2015, 129 Stat. 1679; renumbered § 22903, Pub. L. 115–420, § 7(a)(1), Jan. 3, 2019, 132 Stat. 5445.)

history & why it existsrecord from the source credit
  • 2008Enacted · Pub. L. 110-432 · 122 Stat. 4941
  • 2015Amended · Pub. L. 114-94 · 129 Stat. 1679
  • 2019Amended · Pub. L. 115-420 · 132 Stat. 5445

A history note hasn’t been published yet. The record shows enactment by Pub. L. 110-432 on 2008-10-16.

all 0 arguments · sorted by: best

0/280

no arguments yet — make the first case