16 U.S.C. § 831o — Completion of unfinished plants authorized
submitted 93 years ago by ch. 32 to r/title-16-CONSERVATION · 69 words · no verdicts yet
This section authorizes completion of the unfinished plants identified in the section.
The Board, whenever the President deems it advisable, is empowered and directed to complete Dam Numbered 2 at Muscle Shoals, Alabama, and the steam plant at nitrate plant numbered 2, in the vicinity of Muscle Shoals, by installing in Dam Numbered 2 the additional power units according to the plans and specifications of said dam, and the additional power unit in the steam plant at nitrate plant numbered 2.
Source credit: (May 18, 1933, ch. 32, § 16, 48 Stat. 67; Pub. L. 108–447, div. C, title VI, § 603(a)(2), Dec. 8, 2004, 118 Stat. 2966.)
- 1933Enacted · Act of May 18, 1933, ch. 32 · 48 Stat. 67
- 2004Amended · Pub. L. 108-447 · 118 Stat. 2966
A history note hasn’t been published yet. The record shows enactment by ch. 32 on 1933-05-18.