ALLcrimesfood&drugstaxestelecomcommercehealthconservationtransportationagricultureveteransbrowse all titles »
0

30 U.S.C. § 1269 — Release of performance bonds or deposits

submitted 49 years ago by Pub. L. 95-87 to r/title-30-MINERAL-LANDS-AND-MINING · 1,211 words · no verdicts yet

in plain englishAI-generated · not legal advice

This section sets the process for releasing all or part of a coal-mining performance bond. It requires public notice, inspection, standards for partial releases, objections, hearings, and an official record.

(a) Request and notice. A permittee may ask the regulatory authority to release all or part of a performance bond or deposit. Within 30 days after filing, the operator shall submit a newspaper advertisement published at least weekly for four consecutive weeks. It becomes part of the application and must state the exact affected location, acres, permit and approval date, bond amount, part sought for release, reclamation type and dates, and results compared with the approved plan. The applicant must also submit copies of letters notifying adjoining owners, local governments, planning agencies, sewage and water-treatment authorities, or local water companies of the intent to seek release.
(b) Inspection and decision. Within 30 days after receiving the request and notice, the authority shall inspect and evaluate the reclamation, including remaining difficulty, present or likely future surface or subsurface pollution, and estimated pollution-abatement cost. It shall notify the permittee in writing within 60 days after filing if no subsection (f) hearing occurs, or within 30 days after such a hearing.
(c) Release schedule. The authority may release bond money if the covered reclamation meets this chapter. (1) After backfilling, regrading, and drainage control under the plan, it may release 60 percent for the applicable area. (2) After approved revegetation, it may release the amount left after retaining enough for a third party to reestablish vegetation during the operator-responsibility period. Nothing may be released under this paragraph while the land sends excess suspended solids outside the permit area or prime farmland productivity has not returned to equivalent surrounding nonmined land. If a silt dam will remain permanently, the bond portion may be released when sound future maintenance arrangements exist. (3) After all mining and reclamation are successfully complete, the remaining bond may be released, but not before the operator-responsibility period ends and not until every reclamation requirement is met.
(d) Disapproval. The authority shall give written reasons and needed corrective steps and an opportunity for a hearing.
(e) Municipality. When an application is filed, the authority shall notify the municipality by certified mail at least 30 days before release.
(f) Objections and hearing. A person with a valid legal interest that could be harmed, or the responsible head of a government agency with legal jurisdiction, special expertise about the operation’s environmental, social, or economic effects, or authority to enforce environmental standards, may file written objections within 30 days after the last publication. If objections and a hearing request are filed, the authority shall notify interested parties and hold a public hearing within 30 days, at the operation locality or, at the objector’s option, the State capital. The hearing notice must run in a generally circulated local newspaper for two consecutive weeks.
(g) Informal conference. Without harming anyone’s rights or the authority’s duties, the authority may establish an informal conference under section 1263 to resolve objections.
(h) Hearing powers. For the hearing, the authority may administer oaths, subpoena witnesses and written or printed material, compel attendance or production, and take evidence, including inspections of the affected land and nearby operations by the applicant. A verbatim record is required, and a transcript must be provided on a party’s motion or the authority’s order.

the actual law source: uscode.house.gov ↗public domain
(a) Filing of request; submittal of copy of advertisement; notification by letter of intent to seek release

The permittee may file a request with the regulatory authority for the release of all or part of a performance bond or deposit. Within thirty days after any application for bond or deposit release has been filed with the regulatory authority, the operator shall submit a copy of an advertisement placed at least once a week for four successive weeks in a newspaper of general circulation in the locality of the surface coal mining operation. Such advertisement shall be considered part of any bond release application and shall contain a notification of the precise location of the land affected, the number of acres, the permit and the date approved, the amount of the bond filed and the portion sought to be released, and the type and appropriate dates of reclamation work performed, and a description of the results achieved as they relate to the operator’s approved reclamation plan. In addition, as part of any bond release application, the applicant shall submit copies of letters which he has sent to adjoining property owners, local governmental bodies, planning agencies, and sewage and water treatment authorities, or water companies in the locality in which the surface coal mining and reclamation activities took place, notifying them of his intention to seek release from the bond.

(b) Inspection and evaluation; notification of decision

Upon receipt of the notification and request, the regulatory authority shall within thirty days conduct an inspection and evaluation of the reclamation work involved. Such evaluation shall consider, among other things, the degree of difficulty to complete any remaining reclamation, whether pollution of surface and subsurface water is occurring, the probability of continuance of future occurrence of such pollution, and the estimated cost of abating such pollution. The regulatory authority shall notify the permittee in writing of its decision to release or not to release all or part of the performance bond or deposit within sixty days from the filing of the request, if no public hearing is held pursuant to subsection (f), and if there has been a public hearing held pursuant to subsection (f), within thirty days thereafter.

(c) Requirements for release

The regulatory authority may release in whole or in part said bond or deposit if the authority is satisfied the reclamation covered by the bond or deposit or portion thereof has been accomplished as required by this chapter according to the following schedule:

(1)

When the operator completes the backfilling, regrading, and drainage control of a bonded area in accordance with his approved reclamation plan, the release of 60 per centum of the bond or collateral for the applicable permit area.

(2)

After revegetation has been established on the regraded mined lands in accordance with the approved reclamation plan. When determining the amount of bond to be released after successful revegetation has been established, the regulatory authority shall retain that amount of bond for the revegetated area which would be sufficient for a third party to cover the cost of reestablishing reveg­etation and for the period specified for operator responsibility in section 1265 of this title of reestablishing revegetation. No part of the bond or deposit shall be released under this paragraph so long as the lands to which the release would be applicable are contributing suspended solids to streamflow or runoff outside the permit area in excess of the requirements set by section 1265(b)(10) of this title or until soil productivity for prime farm lands has returned to equivalent levels of yield as nonmined land of the same soil type in the surrounding area under equivalent management practices as determined from the soil survey performed pursuant to section 1257(b)(16) of this title. Where a silt dam is to be retained as a permanent impoundment pursuant to section 1265(b)(8) of this title, the portion of bond may be released under this paragraph so long as provisions for sound future maintenance by the operator or the landowner have been made with the regulatory authority.

(3)

When the operator has completed successfully all surface coal mining and reclamation activities, the release of the remaining portion of the bond, but not before the expiration of the period specified for operator responsibility in section 1265 of this title: Provided, however, That no bond shall be fully released until all reclamation requirements of this chapter are fully met.

(d) Notice of disapproval

If the regulatory authority disapproves the application for release of the bond or portion thereof, the authority shall notify the permittee, in writing, stating the reasons for disapproval and recommending corrective actions necessary to secure said release and allowing opportunity for a public hearing.

(e) Notice to municipality

When any application for total or partial bond release is filed with the regulatory authority, the regulatory authority shall notify the municipality in which a surface coal mining operation is located by certified mail at least thirty days prior to the release of all or a portion of the bond.

(f) Objections to release; hearing

Any person with a valid legal interest which might be adversely affected by release of the bond or the responsible officer or head of any Federal, State, or local governmental agency which has jurisdiction by law or special expertise with respect to any environmental, social, or economic impact involved in the operation, or is authorized to develop and enforce environmental standards with respect to such operations shall have the right to file written objections to the proposed release from bond to the regulatory authority within thirty days after the last publication of the above notice. If written objections are filed, and a hearing requested, the regulatory authority shall inform all the interested parties, of the time and place of the hearing, and hold a public hearing in the locality of the surface coal mining operation proposed for bond release within thirty days of the request for such hearing. The date, time, and location of such public hearings shall be advertised by the regulatory authority in a newspaper of general circulation in the locality for two consecutive weeks, and shall hold a public hearing in the locality of the surface coal mining operation proposed for bond release or at the State capital at the option of the objector, within thirty days of the request for such hearing.

(g) Informal conference

Without prejudice to the rights of the objectors, the applicant, or the responsibilities of the regulatory authority pursuant to this section, the regulatory authority may establish an informal conference as provided in section 1263 of this title to resolve such written objections.

(h) Power of regulatory authority with respect to informal conference

For the purpose of such hearing the regulatory authority shall have the authority and is hereby empowered to administer oaths, subpena witnesses, or written or printed materials, compel the attendance of witnesses, or production of the materials, and take evidence including but not limited to inspections of the land affected and other surface coal mining operations carried on by the applicant in the general vicinity. A verbatim record of each public hearing required by this chapter shall be made, and a transcript made available on the motion of any party or by order of the regulatory authority.

Source credit: (Pub. L. 95–87, title V, § 519, Aug. 3, 1977, 91 Stat. 501.)

history & why it existsrecord from the source credit
  • 1977Enacted · Pub. L. 95-87 · 91 Stat. 501

A history note hasn’t been published yet. The record shows enactment by Pub. L. 95-87 on 1977-08-03.

all 0 arguments · sorted by: best

0/280

no arguments yet — make the first case