33 U.S.C. § 701b–16 — Management of flood risk reduction projects
submitted 12 years ago by Pub. L. 113-121 to r/title-33-NAVIGATION-AND-NAVIGABLE-WATERS · 130 words · no verdicts yet
The Secretary may manage multiple nearby flood projects as one program, and navigation-caused work uses the navigation project’s cost-sharing rules.
(a) At the affected non-Federal interests’ request, the Secretary must consider two or more flood-control projects in the same geographic area as one program for budgeting or project management if doing so is compatible with their authorized purposes. (b)(1) If work is needed solely because a navigation project affected one of those projects, its cost must be shared under the navigation project’s rules. (2) Amounts available under subsection (a) may pay for that work.
If 2 or more flood control projects are located within the same geographic area, the Secretary shall, at the request of the non-Federal interests for the affected projects, consider those projects as a single program for budgetary or project management purposes, if the Secretary determines that doing so would not be incompatible with the authorized project purposes.
If any work on a project to which subsection (a) applies is required solely because of impacts to that project from a navigation project, the cost of carrying out that work shall be shared in accordance with the cost-sharing requirements for the navigation project.
Work described in paragraph (1) may be carried out using amounts made available under subsection (a).
Source credit: (Pub. L. 113–121, title III, § 3012, June 10, 2014, 128 Stat. 1284.)
- 2014Enacted · Pub. L. 113-121 · 128 Stat. 1284