33 U.S.C. § 891d — Contract authority
submitted 34 years ago by Pub. L. 102-567 to r/title-33-NAVIGATION-AND-NAVIGABLE-WATERS · 485 words · no verdicts yet
The Secretary may acquire NOAA vessels through multiyear purchase, lease, lease-purchase, or other contracts. Such contracts require findings about expected congressional funding and the benefit of competition and efficiency, and they must contain specified funding, term, and termination limits.
(a) Multiyear contracts. Subject to paragraphs (2) and (3), the Secretary may acquire vessels for the NOAA fleet by purchase, lease, lease-purchase, or another method under one or more multiyear contracts, despite the listed funding and procurement laws. (2) The Secretary may sign such a contract only after finding that Congress is reasonably expected to provide the funding needed to avoid ending it and that it serves the United States by encouraging competition and efficient NOAA operations. (3) The contract must say that payments for each fiscal year depend on advance appropriations, state its term, and limit the United States' liability if it ends early to the lesser of the contract's stated termination amount or the unobligated amounts appropriated before termination for the contract or that kind of acquisition. (b) Service contracts. Despite other law, the Secretary may make multiyear contracts of no more than 7 years for oceanographic research, fisheries research, or mapping and charting services if the Secretary finds that doing so is in the public interest and either the contract costs less than NOAA providing the services with its vessels, including operation, maintenance, and personnel costs, or NOAA vessels are unavailable or unable to provide them. (c) Bonding authority. For construction, alteration, repair, or maintenance of a NOAA vessel, the Secretary may not require a bid, payment, performance, completion, or other surety bond above 20 percent of the base contract quantity's value, excluding options, unless the Secretary finds that the requirement will not keep a responsible bidder or offeror from competing.
Subject to paragraphs (2) and (3), and notwithstanding section 1341 of title 31 and subsections (a) and (b) of section 6301 of title 41, the Secretary may acquire vessels for the NOAA fleet by purchase, lease, lease-purchase, or otherwise, under one or more multiyear contracts.
The Secretary may not enter into a contract pursuant to this subsection unless the Secretary finds with respect to that contract that—
there is a reasonable expectation that throughout the contemplated contract period the Secretary will request from Congress funding for the contract at the level required to avoid contract termination; and
the use of the contract will promote the best interests of the United States by encouraging competition and promoting economic efficiency in the operation of the NOAA fleet.
The Secretary may not enter into a contract pursuant to this subsection unless the contract includes—
a provision under which the obligation of the United States to make payments under the contract for any fiscal year is subject to the availability of appropriations provided in advance for those payments;
a provision that specifies the term of effectiveness of the contract; and
appropriate provisions under which, in case of any termination of the contract before the end of the term specified pursuant to subparagraph (B), the United States shall only be liable for the lesser of—
an amount specified in the contract for such a termination; or
amounts that—
were appropriated before the date of the termination for the performance of the contract or for procurement of the type of acquisition covered by the contract; and
are unobligated on the date of the termination.
Notwithstanding any other provision of law, the Secretary may enter into multiyear contracts for oceanographic research, fisheries research, and mapping and charting services to assist the Secretary in fulfilling NOAA missions. The Secretary may only enter into these contracts if—
the Secretary finds that it is in the public interest to do so;
the contract is for not more than 7 years; and
the cost of the contract is less than the cost (including the cost of operation, maintenance, and personnel) to the NOAA of obtaining those services on NOAA vessels; or
NOAA vessels are not available or cannot provide those services.
Notwithstanding any other law, the Secretary may not require a contractor for the construction, alteration, repair or maintenance of a NOAA vessel to provide a bid bond, payment bond, performance bond, completion bond, or other surety instrument in an amount greater than 20 percent of the value of the base contract quantity (excluding options) unless the Secretary determines that requiring an instrument in that amount will not prevent a responsible bidder or offeror from competing for the award of the contract.
Source credit: (Pub. L. 102–567, title VI, § 606, Oct. 29, 1992, 106 Stat. 4301.)
- 1992Enacted · Pub. L. 102-567 · 106 Stat. 4301
A history note hasn’t been published yet. The record shows enactment by Pub. L. 102-567 on 1992-10-29.
all 0 arguments · sorted by: best
no arguments yet — make the first case