40 U.S.C. § 3143 — Termination of work on failure to pay agreed wages
submitted 24 years ago by Pub. L. 107-217 to r/title-40-PUBLIC-BUILDINGS-PROPERTY-AND-WORKS · 133 words · no verdicts yet
Covered contracts must let the Government stop work when required wages are not paid. The contractor and sureties must pay extra completion costs.
Every covered contract must provide that, when the contracting officer finds a site laborer or mechanic was or is paid less than the required wage, the Government may by written notice end the contractor’s right to continue the work or affected part. The Government may complete it by contract or otherwise, and the contractor and sureties are liable for excess costs.
Every contract within the scope of this subchapter shall contain a provision that if the contracting officer finds that any laborer or mechanic employed by the contractor or any subcontractor directly on the site of the work covered by the contract has been or is being paid a rate of wages* less than the rate of wages required by the contract to be paid, the Federal Government* by written notice to the contractor may terminate the contractor’s right to proceed with the work or the part of the work as to which there has been a failure to pay the required wages. The Government may have the work completed, by contract or otherwise, and the contractor and the contractor’s sureties shall be liable to the Government for any excess costs the Government incurs.
Source credit: (Pub. L. 107–217, Aug. 21, 2002, 116 Stat. 1151.)
- 2002Enacted · Pub. L. 107-217 · 116 Stat. 1151
A history note hasn’t been published yet. The record shows enactment by Pub. L. 107-217 on 2002-08-21.
all 0 arguments · sorted by: best
no arguments yet — make the first case