41 U.S.C. § 4504Conditions for progress payments

submitted 15 years ago by Pub. L. 111-350 to r/title-41-PUBLIC-CONTRACTS · 134 words · no verdicts yet

in plain englishAI-generated · not legal advice

A translation hasn’t been published for this section yet. The official text below is complete and authoritative.

the actual law source: uscode.house.gov ↗public domain
(a)Payment Commensurate With Work.—

The executive agency shall ensure that a payment for work in progress (including materials, labor, and other items) under a contract of an executive agency that provides for those payments is commensurate with the work accomplished that meets standards established under the contract. The contractor shall provide information and evidence the executive agency determines is necessary to permit the executive agency to carry out this subsection.

(b)Limitation.—

The executive agency shall ensure that progress payments referred to in subsection (a) are not made for more than 80 percent of the work accomplished under the contract as long as the executive agency has not made the contractual terms, specifications, and price definite.

(c)Application.—

This section applies to a contract in an amount greater than $25,000.

Source credit: (Pub. L. 111–350, § 3, Jan. 4, 2011, 124 Stat. 3791.)

history & why it existsrecord from the source credit
  • 2011Enacted · Pub. L. 111-350 · 124 Stat. 3791

A history note hasn’t been published yet. The record shows enactment by Pub. L. 111-350 on 2011-01-04.