42 U.S.C. § 18861 — Office of Clean Energy Demonstrations
submitted 5 years ago by Pub. L. 117-58 to r/title-42-THE-PUBLIC-HEALTH-AND-WELFARE · 673 words · no verdicts yet
This section creates a Department program to evaluate and oversee covered demonstration projects, including costs, milestones, progress, and possible termination.
(a) “Covered project*” means a Department demonstration project receiving or eligible for Secretary* funding and authorized by this division or the Energy Act of 2020. The stray footnote marker in the supplied text is ignored. “Program” means the program under subsection (b). (b) The Secretary, coordinating with relevant Department offices including Technology Transitions, the Loan Program Office, and applied program offices, must establish a program to manage and oversee covered projects. It must evaluate proposals before selection, independently oversee funded projects, and maintain a balanced investment portfolio. (c) The Secretary must appoint a program head. Working with relevant offices, that person must evaluate scope, specifications, design maturity, funding, costs, schedule, milestones, and potential for commercial success based on economic and policy projections; develop independent cost estimates when appropriate; recommend funding; oversee funded projects and compare estimated with actual costs; review ongoing projects against schedules and technical and financial milestones and give the reviews to the Secretary; and use lessons learned to improve evaluation and oversight. (d) The Secretary may hire personnel, including under section 19321. (e) The Secretary may have the program directly solicit, select, and manage covered projects. (f) After an unfavorable review, the Secretary or designee may stop funding and move remaining money to new or existing projects of that office. (g) The program head must coordinate with Department project and acquisition-management entities, including the Office of Project Management, and relevant professional organizations. (h) The Secretary’s updated technology-transfer execution-plan report must describe program implementation and progress, covered projects, and each review. Within 3 years after November 15, 2021, the Comptroller General must report to the listed congressional committees on the program’s operation, evaluation and oversight processes, and recommended process or structural changes. (i) Omitted.
In this section:
The term “covered project” means a demonstration project of the Department that—
receives or is eligible to receive funding from the Secretary*; and
is authorized under—
this division; or
the Energy Act of 2020 (Public Law 116–260; 134 Stat. 1182).1
The term “program” means the program established under subsection (b).
The Secretary, in coordination with the heads of relevant program offices of the Department, including the Office of Technology Transitions, the Loan Program Office, and all applied program offices, shall establish a program to conduct project management and oversight of covered projects, including by—
conducting evaluations of proposals for covered projects before the selection of a covered project for funding;
conducting independent oversight of the execution of a covered project after funding has been awarded for that covered project; and
ensuring a balanced portfolio of investments in covered projects.
The Secretary shall appoint a head of the program who shall, in coordination with the heads of relevant program offices of the Department—
evaluate proposals for covered projects, including scope, technical specifications, maturity of design, funding profile, estimated costs, proposed schedule, proposed technical and financial milestones, and potential for commercial success based on economic and policy projections;
develop independent cost estimates for a proposal for a covered project, if appropriate;
recommend to the head of a program office of the Department, as appropriate, whether to fund a proposal for a covered project;
oversee the execution of covered projects that receive funding from the Secretary, including reconciling estimated costs as compared to actual costs;
conduct reviews of ongoing covered projects, including—
evaluating the progress of a covered project based on the proposed schedule and technical and financial milestones; and
providing the evaluations under subparagraph (A) to the Secretary; and
assess the lessons learned in overseeing covered projects and implement improvements in the process of evaluating and overseeing covered projects.
To carry out the program, the Secretary may hire appropriate personnel, including by using the authorities in section 19321 of this title, to perform the duties of the program.
The Secretary may solicit, select, and manage covered projects directly through the program.
Should an ongoing covered project receive an unfavorable review under subsection (c)(5), the Secretary or their designee may cease funding the covered project and reallocate the remaining funds to new or existing covered projects carried out by that program office.
In carrying out the program, the head of the program shall coordinate with—
project management and acquisition management entities with the Department, including the Office of Project Management; and
professional organizations in project management, construction, cost estimation, and other relevant fields.
In accordance with section 16391a of this title, the Secretary shall include in each updated technology transfer execution plan submitted under subsection (h)(2) of section 16391 of this title information on the implementation of and progress made under the program, including, for the year covered by the report—
the covered projects under the purview of the program; and
the review of each covered project carried out under subsection (c)(5).
Not later than 3 years after November 15, 2021, the Comptroller General of the United States shall submit to the Committee on Energy and Natural Resources of the Senate and the Committee on Science, Space, and Technology of the House of Representatives a report evaluating the operation of the program, including—
a description of the processes and procedures used by the program to evaluate proposals of covered projects and the oversight of covered projects; and
any recommended changes in the program, including changes to—
the processes and procedures described in subparagraph (A); and
the structure of the program, for the purpose of better carrying out the program.
Source credit: (Pub. L. 117–58, div. D, title XII, § 41201, Nov. 15, 2021, 135 Stat. 1130; Pub. L. 117–167, div. B, title VI, § 10723, Aug. 9, 2022, 136 Stat. 1709.)
- 2021Enacted · Pub. L. 117-58 · 135 Stat. 1130
- 2022Amended · Pub. L. 117-167 · 136 Stat. 1709
A history note hasn’t been published yet. The record shows enactment by Pub. L. 117-58 on 2021-11-15.