42 U.S.C. § 5189f — Public assistance program alternative procedures
submitted 13 years ago by Pub. L. 93-288 to r/title-42-THE-PUBLIC-HEALTH-AND-WELFARE · 1,224 words · no verdicts yet
This section permits alternative procedures for administering certain disaster assistance. Participation is optional for eligible governments and private nonprofit facilities. The procedures may use fixed estimates, consolidated projects, special treatment of savings, expert review, and other tools described below.
This section permits alternative procedures for administering certain disaster assistance. Participation is optional for eligible governments and private nonprofit facilities. The procedures may use fixed estimates, consolidated projects, special treatment* of savings, expert review, and other tools described below.
(a) Approval of projects. Acting through the FEMA Administrator*, the President may approve projects under these alternative procedures for any major disaster or emergency declared on or after January 29, 2013. The Administrator may also use them for a disaster or emergency declared before the Act’s enactment if construction had not begun by the Act’s enactment date.
(b) Adoption. In coordination with States, tribal and local governments, and owners or operators of private nonprofit facilities, the Administrator may adopt alternative procedures for administering assistance under sections 5170b(a)(3)(A), 5172, 5173, and 5192(a)(5).
(c) Goals of procedures. The procedures must advance these goals—
(1) reduce the Federal Government’s cost of providing the assistance;
(2) make administration more flexible;
(3) speed delivery of assistance to a State*, tribal or local government*, or private nonprofit facility* owner* or operator; and
(4) give those governments and owners or operators financial rewards and penalties for completing projects with the assistance on time and cost-effectively.
(d) Participation.
(1) In general. A State, tribal or local government, or private nonprofit facility owner or operator chooses whether to participate, following procedures set by the Administrator.
(2) No conditions. The President may not make Federal assistance under this chapter conditional on a State, local, or Indian tribal government*, or private nonprofit facility owner or operator choosing to participate.
(e) Minimum procedures. The procedures must include the following:
(1) Repair, restoration, and replacement of damaged facilities under section 5172.
(A) Grants may be based on fixed estimates if the government or private nonprofit facility owner or operator agrees to pay any actual costs above the estimate.
(B) The procedures must let the government or owner or operator choose an unreduced in-lieu payment based on estimates of—
(i) repairing, restoring, rebuilding, or replacing its public facility; and
(ii) management expenses.
(C) To the extent the Administrator finds appropriate, the procedures may combine the facilities of a government or private nonprofit facility owner or operator into one project* using the adopted estimates.
(D) If a completed project costs less than estimated, the Administrator may let a grantee or subgrantee use all or part of the extra money for—
(i) cost-effective work that reduces the risk of future disaster damage, hardship, or suffering; and
(ii) other work improving future Public Assistance operations or planning.
(E) When determining eligible costs under section 5172, the Administrator must make an independent expert panel available at the applicant’s request when the Administrator’s estimate or a certified estimate by the applicant’s professionally licensed engineers puts the eligible Federal share at $5,000,000 or more. The panel must validate the estimated eligible cost consistently with applicable regulations and policies implementing this section.
(F) When determining eligible costs under section 5172, the Administrator must, at the applicant’s request, consider properly prepared and certified estimates by professionally licensed engineers mutually agreed on by the Administrator and applicant, if the estimates follow applicable regulations, policy, and guidance.
(G) Once a professionally licensed engineer certifies an estimate and the Administrator accepts it, the estimate used for a grant under this section is presumed to show reasonable eligible costs, unless there is evidence of fraud.
(2) Debris removal under sections 5170b(a)(3)(A), 5173, and 5192(a)(5).
(A) Grants may be based on fixed estimates to reward or discourage timely or cost-effective completion if the government or private nonprofit facility owner or operator agrees to pay any actual costs above the estimate.
(B) The Federal share for removing debris and wreckage may be set on a sliding scale based on the time taken to finish the removal.
(C) Program income from recycled debris may be used without reducing the grant.
(D) Base and overtime wages may be reimbursed for employees and extra hires of a government or private nonprofit facility owner or operator who perform or administer debris and wreckage removal.
(E) The procedures may reward a State, tribal, or local government for having an Administrator-approved debris-management plan and one or more prequalified debris-removal contractors before the major disaster is declared.
(F) If a project under subparagraph (A) costs less than estimated, the Administrator may let a grantee or subgrantee use all or part of the extra money for—
(i) debris-management planning;
(ii) buying debris-management equipment for current or future use; and
(iii) other activities the Administrator determines will improve future debris-removal operations.
(f) Waiver authority. Until the Administrator issues regulations implementing this section, the Administrator may—
(1) waive notice-and-comment rulemaking if the Administrator finds the waiver needed to implement this section quickly; and
(2) run these alternative procedures as a pilot program.
(g) Overtime payments. Reimbursement guidelines under subsection (e)(2)(D) must ensure that no State or local government is denied reimbursement for overtime payments required by the Fair Labor Standards Act of 1938.
(h) Report.
(1) In general. Between three and five years after January 29, 2013, the Inspector General of the Department of Homeland Security must send the Senate Committee on Homeland Security and Governmental Affairs and the House Committee on Transportation and Infrastructure a report about the alternative procedures for repairing, restoring, and replacing damaged facilities under section 5172.
(2) Contents. The report must assess how effective the procedures were, including—
(A) whether they improved the overall speed of disaster recovery;
(B) how accurate the estimates were;
(C) whether the financial rewards and penalties worked;
(D) whether the procedures were cost-effective;
(E) whether the independent expert panel in subsection (e)(1)(E) worked; and
(F) whether the procedures should continue and any recommended changes.
This section does not define “major disaster,” “emergency,” “alternative procedures,” “fixed estimate,” “in-lieu contribution,” “program income,” “pre-qualified,” “fraud,” or “cost-effective.”
The President, acting through the Administrator* of the Federal Emergency Management Agency, may approve projects under the alternative procedures adopted under this section for any major disaster or emergency declared on or after January 29, 2013. The Administrator may also apply the alternate procedures adopted under this section to a major disaster or emergency declared before enactment of this Act for which construction has not begun as of the date of enactment of this Act.1
The Administrator, in coordination with States, tribal and local governments, and owners or operators of private nonprofit facilities, may adopt alternative procedures to administer assistance provided under sections 5170b(a)(3)(A), 5172, 5173, and 5192(a)(5) of this title.
The alternative procedures adopted under subsection (a) shall further the goals of—
reducing the costs to the Federal Government of providing such assistance;
increasing flexibility in the administration of such assistance;
expediting the provision of such assistance to a State*, tribal or local government*, or owner* or operator of a private nonprofit facility*; and
providing financial incentives and disincentives for a State, tribal or local government, or owner or operator of a private nonprofit facility for the timely and cost-effective completion of projects with such assistance.
Participation in the alternative procedures adopted under this section shall be at the election of a State, tribal or local government, or owner or operator of a private nonprofit facility consistent with procedures determined by the Administrator.
The President may not condition the provision of Federal assistance under this chapter on the election by a State, local, or Indian tribal government*, or owner or operator of a private nonprofit facility to participate in the alternative procedures adopted under this section.
The alternative procedures adopted under this section shall include the following:
For repair, restoration, and replacement of damaged facilities under section 5172 of this title—
making grants on the basis of fixed estimates, if the State, tribal or local government, or owner or operator of the private nonprofit facility agrees to be responsible for any actual costs that exceed the estimate;
providing an option for a State, tribal or local government, or owner or operator of a private nonprofit facility to elect to receive an in-lieu contribution, without reduction, on the basis of estimates of—
the cost of repair, restoration, reconstruction, or replacement of a public facility owned or controlled by the State, tribal or local government or owner or operator of a private nonprofit facility; and
management expenses;
consolidating, to the extent determined appropriate by the Administrator, the facilities of a State, tribal or local government, or owner or operator of a private nonprofit facility as a single project* based upon the estimates adopted under the procedures;
if the actual costs of a project completed under the procedures are less than the estimated costs thereof, the Administrator may permit a grantee or subgrantee to use all or part of the excess funds for—
cost-effective activities that reduce the risk of future damage, hardship, or suffering from a major disaster; and
other activities to improve future Public Assistance operations or planning;
in determining eligible costs under section 5172 of this title, the Administrator shall make available, at an applicant’s request and where the Administrator or the certified cost estimate prepared by the applicant’s professionally licensed engineers has estimated an eligible Federal share for a project of at least $5,000,000, an independent expert panel to validate the estimated eligible cost consistent with applicable regulations and policies implementing this section;
in determining eligible costs under section 5172 of this title, the Administrator shall, at the applicant’s request, consider properly conducted and certified cost estimates prepared by professionally licensed engineers (mutually agreed upon by the Administrator and the applicant), to the extent that such estimates comply with applicable regulations, policy, and guidance; and
once certified by a professionally licensed engineer and accepted by the Administrator, the estimates on which grants made pursuant to this section are based shall be presumed to be reasonable and eligible costs, as long as there is no evidence of fraud.
For debris removal under sections 5170b(a)(3)(A), 5173, and 5192(a)(5) of this title—
making grants on the basis of fixed estimates to provide financial incentives and disincentives for the timely or cost-effective completion if the State, tribal or local government, or owner or operator of the private nonprofit facility agrees to be responsible to pay for any actual costs that exceed the estimate;
using a sliding scale for determining the Federal share for removal of debris and wreckage based on the time it takes to complete debris and wreckage removal;
allowing use of program income from recycled debris without offset to the grant amount;
reimbursing base and overtime wages for employees and extra hires of a State, tribal or local government, or owner or operator of a private nonprofit facility performing or administering debris and wreckage removal;
providing incentives to a State or tribal or local government to have a debris management plan approved by the Administrator and have pre-qualified 1 or more debris and wreckage removal contractors before the date of declaration of the major disaster; and
if the actual costs of projects under subparagraph (A) are less than the estimated costs of the project, the Administrator may permit a grantee or subgrantee to use all or part of the excess funds for—
debris management planning;
acquisition of debris management equipment for current or future use; and
other activities to improve future debris removal operations, as determined by the Administrator.
Until such time as the Administrator promulgates regulations to implement this section, the Administrator may—
waive notice and comment rulemaking, if the Administrator determines the waiver is necessary to expeditiously implement this section; and
carry out the alternative procedures under this section as a pilot program.
The guidelines for reimbursement for costs under subsection (e)(2)(D) shall ensure that no State or local government is denied reimbursement for overtime payments that are required pursuant to the Fair Labor Standards Act of 1938 (29 U.S.C. 201 et seq.).
Not earlier than 3 years, and not later than 5 years, after January 29, 2013, the Inspector General of the Department of Homeland Security shall submit to the Committee on Homeland Security and Governmental Affairs of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a report on the alternative procedures for the repair, restoration, and replacement of damaged facilities under section 5172 of this title authorized under this section.
The report shall contain an assessment of the effectiveness of the alternative procedures, including—
whether the alternative procedures helped to improve the general speed of disaster recovery;
the accuracy of the estimates relied upon;
whether the financial incentives and disincentives were effective;
whether the alternative procedures were cost effective;
whether the independent expert panel described in subsection (e)(1)(E) was effective; and
recommendations for whether the alternative procedures should be continued and any recommendations for changes to the alternative procedures.
Source credit: (Pub. L. 93–288, title IV, § 428, as added Pub. L. 113–2, div. B, § 1102(2), Jan. 29, 2013, 127 Stat. 39; amended Pub. L. 115–254, div. D, § 1207(c), (d), Oct. 5, 2018, 132 Stat. 3440, 3441.)
- 2013Enacted · Pub. L. 93-288 · 127 Stat. 39
- 2018Amended · Pub. L. 115-254 · 132 Stat. 3440, 3441
A history note hasn’t been published yet. The record shows enactment by Pub. L. 93-288 on 2013-01-29.
all 0 arguments · sorted by: best
no arguments yet — make the first case