49 U.S.C. § 22903 — Project management oversight
submitted 18 years ago by Pub. L. 110-432 to r/title-49-TRANSPORTATION · 279 words · no verdicts yet
To get federal money for a major capital project, an applicant must have a Secretary-approved project management plan. That plan must cover staffing, budgets, schedules, and quality control, among other things. Recipients must also give the Secretary access to construction sites and records when reasonably needed.
To receive Federal financial assistance for a major capital project* under this chapter, an applicant* must prepare and carry out a project management plan approved by the Secretary of Transportation. The plan shall provide for—
adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;
a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;
a construction schedule for the project;
a document control procedure and recordkeeping system;
a change order procedure that includes a documented, systematic approach to handling the construction change orders;
organizational structures, management skills, and staffing levels required throughout the construction phase;
quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;
material testing policies and procedures;
internal plan implementation and reporting requirements;
criteria and procedures to be used for testing the operational system or its major components;
periodic updates of the plan, especially related to project budget and project schedule, financing, and ridership estimates; and
the recipient’s commitment to submit periodically a project budget and project schedule to the Secretary.
Repealed. Pub. L. 114–94, div. A, title XI, § 11316(p), Dec. 4, 2015, 129 Stat. 1679]
Each recipient of assistance under this chapter shall provide the Secretary and a contractor the Secretary chooses under subsection (b) of this section with access to the construction sites and records of the recipient when reasonably necessary.
Source credit: (Added Pub. L. 110–432, div. B, title III, § 301(a), Oct. 16, 2008, 122 Stat. 4941, § 24403; amended Pub. L. 114–94, div. A, title XI, § 11316(p), Dec. 4, 2015, 129 Stat. 1679; renumbered § 22903, Pub. L. 115–420, § 7(a)(1), Jan. 3, 2019, 132 Stat. 5445.)
- 2008Enacted · Pub. L. 110-432 · 122 Stat. 4941
- 2015Amended · Pub. L. 114-94 · 129 Stat. 1679
- 2019Amended · Pub. L. 115-420 · 132 Stat. 5445
A history note hasn’t been published yet. The record shows enactment by Pub. L. 110-432 on 2008-10-16.
all 0 arguments · sorted by: best
no arguments yet — make the first case