ALLcrimesfood&drugstaxestelecomcommercehealthconservationtransportationagricultureveteransbrowse all titles »
0

49 U.S.C. § 47119Terminal development costs

submitted 32 years ago by Pub. L. 103-272 to r/title-49-TRANSPORTATION · 1,344 words · no verdicts yet

in plain englishAI-generated · not legal advice

This section explains which airport terminal projects the federal government can help pay for. Airports must already meet safety and security requirements before getting terminal money, with extra rules for smaller airports. Special funds also help repay old terminal construction loans and support lactation rooms and changing stations.

(a) Terminal Development Projects — (1) The Secretary may approve a terminal development project, including multimodal terminal development, in a nonrevenue-producing public-use area of a commercial service airport (A) if the sponsor certifies that, as of the application date, the airport already has (i) all safety equipment required for its certification under section 44706, (ii) all security equipment required by regulation, and (iii) a way for passengers to reach areas where they board or exit aircraft that are not air carrier aircraft; (B) if the cost directly relates to (i) moving passengers and baggage within the airport, including vehicles between terminal facilities and between terminals and aircraft, or (ii) installing security cameras in the public interior or exterior of the terminal; and (C) under terms that protect the government's interests. (2) In revenue-producing areas and nonrevenue-producing parking lots, the Secretary may also approve costs there if (A) the airport has no more than 0.05 percent of total U.S. passenger boardings, except as section 47108(e)(3) allows, and (B) the sponsor certifies that approving this will not delay any needed project affecting safety, security, or capacity. (3) The Secretary may also approve a terminal development project for building or installing a lactation area, as defined in section 47107(w), at a commercial service airport. (4) The Secretary may likewise approve one for a universal changing station, as defined in section 47107(y). (b) Repaying Borrowed Money — (1) For terminal development carried out between June 30, 1970, and July 12, 1976, apportioned money made available to the sponsor can immediately repay money the sponsor borrowed for that work, if those costs would have been allowable under section 47110(d) had they been incurred after September 3, 1982. (2) For terminal development at a nonhub airport between January 1, 1992, and October 31, 1992, apportioned money can likewise immediately repay borrowed money used for that work, if the costs would be allowable under section 47110(d). (3) For terminal development at a primary airport carried out between January 2003 and August 2004, where the airport was a nonhub airport in the most recent apportionment calculation and was designated under section 47118 in fiscal year 2003, apportioned money, or money available under paragraph (3) of this subsection, can immediately repay borrowed money used for that work, if the costs would be allowable under subsection (a). (4) Any of these repayment grants require that (A) the sponsor submit the certification required under subsection (a); (B) the Secretary decide that using the money this way will not delay another development project outside the terminal area; and (C) the airport not use development funds for additional terminal projects for at least one year after the repayment grant is used. (5) These repayment grants are also subject to the dollar limits in subsections (c)(1) and (c)(2). (c) Availability of Amounts — In a fiscal year, the Secretary may make available (1) to a primary airport sponsor, any part of its own apportioned money under section 47114(c)(1) for costs allowable under subsection (a); (2) with the Secretary's approval, not more than $200,000 from the discretionary fund (A) to a nonprimary commercial service airport sponsor for subsection (a) costs, and (B) to a reliever airport sponsor for the same kinds of costs, including costs allowable for a commercial service airport with no more than 0.05 percent of total U.S. boardings; (3) for a primary airport with no more than 0.05 percent of total U.S. boardings, any part of the discretionary fund or small airport fund money for subsection (a) costs; (4) not more than $25,000,000 for subsection (a) costs at commercial service airports that were not eligible for terminal-development assistance during the fiscal year ending September 30, 1980, under the old Airport and Airway Development Act of 1970; (5) to a nonprimary airport sponsor, any part of its money apportioned under sections 47114(c) and 47114(d)(2)(A) for subsection (a) costs; or (6) not more than $20,000,000 from the discretionary fund to a nonprimary airport sponsor for terminal development costs allowable under subsection (a), if the Secretary determines — based on enplanement trends, a completed air service development study, airline commitments to provide service accommodating at least 10,000 annual enplanements, the sponsor's documented commitment to fund the rest of the project, and a favorable environmental finding including all required permits — that the airport is reasonably expected to reach primary status within three calendar years of the grant. (d) Nonhub Airports — For a commercial service airport with less than 0.05 percent of total U.S. enplanements, the Secretary may approve the use of subsection (a) amounts even without meeting the requirements otherwise imposed by sections 47107(a)(17), 47112, and 47113. (e) Determination of Passenger Boarding at Commercial Service Airports — To decide whether an amount may be distributed for a fiscal year from the discretionary fund under subsection (b)(2)(A) to a commercial service airport, the Secretary determines whether a public airport is a commercial service airport based on its passenger boardings and type of air service in the calendar year that includes the first day of that fiscal year, or the preceding calendar year, whichever is more beneficial to the airport. (f) Limitation on Discretionary Funds — The Secretary may distribute no more than $30,000,000 from the discretionary fund for terminal development projects at a nonhub airport or a small hub airport eligible to receive discretionary funds under section 47108(e)(3).
the actual law source: uscode.house.gov ↗public domain
(a)Terminal Development Projects.—
(1)In general.—

The Secretary of Transportation may approve a project for terminal development (including multimodal terminal development) in a nonrevenue-producing public-use area of a commercial service airport—

(A)

if the sponsor certifies that the airport, on the date the grant application is submitted to the Secretary, has—

(i)

all the safety equipment required for certification of the airport under section 44706;

(ii)

all the security equipment required by regulation; and

(iii)

provided for access by passengers to the area of the airport for boarding or exiting aircraft that are not air carrier aircraft;

(B)

if the cost is directly related to—

(i)

moving passengers and baggage in air commerce within the airport, including vehicles for moving passengers between terminal facilities and between terminal facilities and aircraft; or

(ii)

installing security cameras in the public area of the interior and exterior of the terminal; and

(C)

under terms necessary to protect the interests of the Government.

(2)Project in revenue-producing areas and nonrevenue-producing parking lots.—

In making a decision under paragraph (1), the Secretary may approve as allowable costs the expenses of terminal development in a revenue-producing area and construction, reconstruction, repair, and improvement in a nonrevenue-producing parking lot if—

(A)

except as provided in section 47108(e)(3),1 the airport does not have more than .05 percent of the total annual passenger boardings in the United States; and

(B)

the sponsor certifies that any needed airport development project affecting safety, security, or capacity will not be deferred because of the Secretary’s approval.

(3)Lactation areas.—

In addition to the projects described in paragraph (1), the Secretary may approve a project for terminal development for the construction or installation of a lactation area (as defined in section 47107(w)) at a commercial service airport.

(4)Universal changing stations.—

In addition to the projects described in paragraph (1), the Secretary may approve a project for terminal development for the construction or installation of a universal changing station (as defined in section 47107(y)) at a commercial service airport.

(b)Repaying Borrowed Money.—
(1)Terminal development costs incurred after june 30, 1970, and before july 12, 1976.—

An amount apportioned under section 47114 and made available to the sponsor of a commercial service airport at which terminal development was carried out after June 30, 1970, and before July 12, 1976, is available to repay immediately money borrowed and used to pay the costs for such terminal development if those costs would be allowable project costs under section 47110(d) if they had been incurred after September 3, 1982.

(2)Terminal development costs incurred between january 1, 1992, and october 31, 1992.—

An amount apportioned under section 47114 and made available to the sponsor of a nonhub airport at which terminal development was carried out between January 1, 1992, and October 31, 1992, is available to repay immediately money borrowed and to pay the costs for such terminal development if those costs would be allowable project costs under section 47110(d).

(3)Terminal development costs at primary airports.—

An amount apportioned under section 47114 or available under subsection (b)(3) to a primary airport—

(A)

that was a nonhub airport in the most recent year used to calculate apportionments under section 47114;

(B)

that is a designated airport under section 47118 in fiscal year 2003; and

(C)

at which terminal development is carried out between January 2003 and August 2004,

is available to repay immediately money borrowed and used to pay the costs for such terminal development if those costs would be allowable project costs under subsection (a).

(4)Conditions for grant.—

An amount is available for a grant under this subsection only if—

(A)

the sponsor submits the certification required under subsection (a);

(B)

the Secretary decides that using the amount to repay the borrowed money will not defer an airport development project outside the terminal area at that airport; and

(C)

amounts available for airport development under this subchapter will not be used for additional terminal development projects at the airport for at least 1 year beginning on the date the grant is used to repay the borrowed money.

(5)Applicability of certain limitations.—

A grant under this subsection shall be subject to the limitations in subsections (c)(1) and (c)(2).

(c)Availability of Amounts.—

In a fiscal year, the Secretary may make available—

(1)

to a sponsor of a primary airport, any part of amounts apportioned to the sponsor for the fiscal year under section 47114(c)(1) of this title to pay project costs allowable under subsection (a);

(2)

on approval of the Secretary, not more than $200,000 of the amount that may be distributed for the fiscal year from the discretionary fund established under section 47115 of this title—

(A)

to a sponsor of a nonprimary commercial service airport to pay project costs allowable under subsection (a); and

(B)

to a sponsor of a reliever airport for the types of project costs allowable under subsection (a), including project costs allowable for a commercial service airport that each year does not have more than .05 percent of the total boardings in the United States;

(3)

for use by a primary airport that each year does not have more than .05 percent of the total boardings in the United States, any part of amounts that may be distributed for the fiscal year from the discretionary fund and small airport fund to pay project costs allowable under subsection (a);

(4)

not more than $25,000,000 to pay project costs allowable for the fiscal year under subsection (a) for projects at commercial service airports that were not eligible for assistance for terminal development during the fiscal year ending September 30, 1980, under section 20(b) of the Airport and Airway Development Act of 1970;

(5)

to a sponsor of a nonprimary airport, any part of amounts apportioned to the sponsor for the fiscal year under sections 47114(c) and 47114(d)(2)(A) for project costs allowable under subsection (a); or

(6)

not more than $20,000,000 of the amount that may be distributed for the fiscal year from the discretionary fund established under section 47115, to the sponsor of a nonprimary airport to pay costs allowable under subsection (a) for terminal development projects, if the Secretary determines (which may be based on actual and projected enplanement trends, as well as completion of an air service development study, demonstrated commitment by airlines to provide commercial service accommodating at least 10,000 annual enplanements, the documented commitment of a sponsor to providing the remaining funding to complete the proposed project, and a favorable environmental finding (including all required permits) in support of the proposed project) that the status of the nonprimary airport is reasonably expected to change to primary status based on enplanements for the third calendar year after the issuance of the discretionary grant.

(d)Nonhub Airports.—

With respect to a project at a commercial service airport which annually has less than 0.05 percent of the total enplanements in the United States, the Secretary may approve the use of the amounts described in subsection (a) notwithstanding the requirements of sections 47107(a)(17), 47112, and 47113.

(e)Determination of Passenger Boarding at Commercial Service Airports.—

For the purpose of determining whether an amount may be distributed for a fiscal year from the discretionary fund in accordance with subsection (b)(2)(A) to a commercial service airport, the Secretary shall make the determination of whether or not a public airport is a commercial service airport on the basis of the number of passenger boardings and type of air service at the public airport in the calendar year that includes the first day of such fiscal year or the preceding calendar year, whichever is more beneficial to the airport.

(f) Limitation on Discretionary Funds.—

The Secretary may distribute not more than $30,000,000 from the discretionary fund established under section 47115 for terminal development projects at a nonhub airport or a small hub airport that is eligible to receive discretionary funds under section 47108(e)(3).1

Source credit: (Pub. L. 103–272, § 1(e), July 5, 1994, 108 Stat. 1274; Pub. L. 103–305, title I, § 117, Aug. 23, 1994, 108 Stat. 1579; Pub. L. 103–429, § 6(69), Oct. 31, 1994, 108 Stat. 4387; Pub. L. 106–181, title I, § 152(b), Apr. 5, 2000, 114 Stat. 87; Pub. L. 108–176, title I, §§ 149(d), 166, Dec. 12, 2003, 117 Stat. 2505, 2514; Pub. L. 112–95, title I, § 152(b), Feb. 14, 2012, 126 Stat. 33; Pub. L. 115–254, div. B, title I, §§ 132(b), 138, Oct. 5, 2018, 132 Stat. 3206, 3210; Pub. L. 118–63, title VII, §§ 718, 774(b), May 16, 2024, 138 Stat. 1260, 1298.)

history & why it existsrecord from the source credit
  • 1994Enacted · Pub. L. 103-272 · 108 Stat. 1274
  • 1994Amended · Pub. L. 103-305 · 108 Stat. 1579
  • 1994Amended · Pub. L. 103-429 · 108 Stat. 4387
  • 2000Amended · Pub. L. 106-181 · 114 Stat. 87
  • 2003Amended · Pub. L. 108-176 · 117 Stat. 2505, 2514
  • 2012Amended · Pub. L. 112-95 · 126 Stat. 33
  • 2018Amended · Pub. L. 115-254 · 132 Stat. 3206, 3210
  • 2024Amended · Pub. L. 118-63 · 138 Stat. 1260, 1298

A history note hasn’t been published yet. The record shows enactment by Pub. L. 103-272 on 1994-07-05.

all 0 arguments · sorted by: best

0/280

no arguments yet — make the first case