ALLcrimesfood&drugstaxestelecomcommercehealthconservationtransportationagricultureveteransbrowse all titles »
0

10 U.S.C. § 2922iMultiyear contracts: purchase of electricity from renewable energy sources

submitted 18 years ago by Pub. L. 110-181 to r/title-10-ARMED-FORCES · 192 words · no verdicts yet

in plain englishAI-generated · not legal advice

This section addresses multiyear contracts: purchase of electricity from renewable energy sources. It sets out the rules, duties, permissions, definitions, or other provisions that apply to that subject.

(a) Multiyear Contracts Authorized .— subject to subsection (b), the Secretary of Defense may enter into a contract for a period not to exceed 10 years for the purchase of electricity from sources of renewable energy, as that term is defined in section 203(b)(2) of the Energy Policy Act of 2005 ( 42 U.S.C. 15852(b)(2) ). (b) Limitations on Contracts for Periods in Excess of Five Years .— The Secretary may exercise the authority in subsection (a) to enter into a contract for a period in excess of five years only if the Secretary determines, on the basis of a business case analysis prepared by the Department of Defense, that— (1) the proposed purchase of electricity under such contract is cost effective for the Department of Defense; and (2) it would not be possible to purchase electricity from the source in an economical manner without the use of a contract for a period in excess of five years. (c) Relationship to Other Multiyear Contracting Authority .— Nothing in this section must be read to preclude the Department of Defense from using other multiyear contracting authority of the Department to purchase renewable energy.
the actual law source: uscode.house.gov ↗public domain
(a)Multiyear Contracts Authorized.—

Subject to subsection (b), the Secretary of Defense may enter into a contract for a period not to exceed 10 years for the purchase of electricity from sources of renewable energy, as that term is defined in section 203(b)(2) of the Energy Policy Act of 2005 (42 U.S.C. 15852(b)(2)).

(b)Limitations on Contracts for Periods in Excess of Five Years.—

The Secretary may exercise the authority in subsection (a) to enter into a contract for a period in excess of five years only if the Secretary determines, on the basis of a business case analysis prepared by the Department of Defense, that—

(1)

the proposed purchase of electricity under such contract is cost effective for the Department of Defense; and

(2)

it would not be possible to purchase electricity from the source in an economical manner without the use of a contract for a period in excess of five years.

(c)Relationship to Other Multiyear Contracting Authority.—

Nothing in this section shall be construed to preclude the Department of Defense from using other multiyear contracting authority of the Department to purchase renewable energy.

Source credit: (Added Pub. L. 110–181, div. A, title VIII, § 828(a), Jan. 28, 2008, 122 Stat. 229, § 2410q; renumbered § 2922i, Pub. L. 116–283, div. A, title XVIII, § 1879(a), Jan. 1, 2021, 134 Stat. 4293.)

history & why it existsrecord from the source credit
  • 2008Enacted · Pub. L. 110-181 · 122 Stat. 229
  • 2021Amended · Pub. L. 116-283 · 134 Stat. 4293

A history note hasn’t been published yet. The record shows enactment by Pub. L. 110-181 on 2008-01-28.