10 U.S.C. § 3749 — Burden of proof on contractor
submitted 5 years ago by Pub. L. 116-283 to r/title-10-ARMED-FORCES · 60 words · no verdicts yet
A translation hasn’t been published for this section yet. The official text below is complete and authoritative.
In a proceeding before the Armed Services Board of Contract Appeals, the United States Court of Federal Claims, or any other Federal court in which the reasonableness of indirect costs for which a contractor seeks reimbursement from the Department of Defense is in issue, the burden of proof shall be upon the contractor to establish that those costs are reasonable.
Source credit: (Added and amended Pub. L. 116–283, div. A, title XVIII, § 1832(a), (h), Jan. 1, 2021, 134 Stat. 4218, 4222.)
- 2021Enacted · Pub. L. 116-283 · 134 Stat. 4218, 4222
A history note hasn’t been published yet. The record shows enactment by Pub. L. 116-283 on 2021-01-01.
all 0 arguments · sorted by: best
no arguments yet — make the first case