10 U.S.C. § 6285 — Life-cycle cost estimates of certain atomic energy defense capital assets
submitted 1 year ago by Pub. L. 119-60 to r/title-10-ARMED-FORCES · 165 words · no verdicts yet
This section sets rules concerning life-cycle cost estimates of certain atomic energy defense capital assets. It assigns duties, permissions, limits, definitions, or procedures as stated in the section.
(a) In General .: The Secretary of Energy shall ensure that an independent life-cycle cost estimate under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, of each capital asset described in subsection
(b) is conducted before the asset achieves critical decision 2 in the acquisition process.
(b) Capital Assets Described .: A capital asset described in this subsection is an atomic energy defense capital asset: (1) the total project cost of which exceeds $100,000,000. and (2) the purpose of which is to perform a limited-life, single-purpose mission.
(c) Independent Defined .: For purposes of subsection (a), the term “independent”, with respect to a life-cycle cost estimate of a capital asset, means that the life-cycle cost estimate is prepared by an organization independent of the project sponsor, using the same detailed technical and procurement information as the sponsor, to determine if the life-cycle cost estimate of the sponsor is accurate and reasonable.
The Secretary of Energy shall ensure that an independent life-cycle cost estimate under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, of each capital asset described in subsection (b) is conducted before the asset achieves critical decision 2 in the acquisition process.
A capital asset described in this subsection is an atomic energy defense capital asset—
the total project cost of which exceeds $100,000,000; and
the purpose of which is to perform a limited-life, single-purpose mission.
For purposes of subsection (a), the term “independent”, with respect to a life-cycle cost estimate of a capital asset, means that the life-cycle cost estimate is prepared by an organization independent of the project sponsor, using the same detailed technical and procurement information as the sponsor, to determine if the life-cycle cost estimate of the sponsor is accurate and reasonable.
Source credit: (Added Pub. L. 119–60, div. C, title XXXI, § 3111(a), Dec. 18, 2025, 139 Stat. 1434.)
- 2025Enacted · Pub. L. 119-60 · 139 Stat. 1434
A history note hasn’t been published yet. The record shows enactment by Pub. L. 119-60 on 2025-12-18.
all 0 arguments · sorted by: best
no arguments yet — make the first case