10 U.S.C. § 8669cAssessments required prior to start of construction on first ship of a shipbuilding program

submitted 5 years ago by Pub. L. 117-81 to r/title-10-ARMED-FORCES · 632 words · no verdicts yet

in plain englishAI-generated · not legal advice

The Navy must wait 15 days before starting the first ship of a major shipbuilding program. First the Secretary must report on a production readiness review. The Secretary must also certify the review supports construction and that 95 percent of design drawings are approved.

(a) In General — The Secretary of the Navy cannot approve the start of construction on the first ship of a major shipbuilding program until 15 days have passed since the Secretary did three things: (1) sent Congress's defense committees a report on the results of a production readiness review; (2) certified to those committees that the review's findings support starting construction; and (3) certified that at least 95 percent of all the basic and functional design drawing packages for the ship have final approval. (b) Report — The report required by (a)(1) must cover: (1) how much of the detailed design and production drawings are done, matching the shipbuilding contract; (2) whether the shipyard's facilities and workers are ready to start building; (3) the Navy's estimated delivery date and any risks to that date; (4) whether good processes and metrics exist to track program risk; (5) for the first ship, the Navy's plans to oversee and document construction so the design supports the schedule; (6) a definition of "start of construction" for the first ship — one that does not mean a point after 5 percent of lightship displacement is complete, and does not mean advance procurement or advance construction; (7) any hull or superstructure fabrication that happens before the Secretary sends the certifications in (a)(2) and (a)(3); and (8) how much vendor and government information supports the design's maturity, including whether vendor selection and specifications are final for major systems and equipment, and the status of factory acceptance testing. (c) Definitions — For subsection (a): "Basic and functional design" means, for most vessels, computer-aided-model design, and for manned surface and undersea combatants, three-dimensional computer modeling, that supports the hull structure, sets the vessel's hydrodynamics, and positions and routes all major utility systems like electricity and water. "First ship" means either the first ship built under a shipbuilding program, or a ship built at a shipyard that has not previously started that program. "Major shipbuilding program" means a program to build combat and support vessels reported in the Navy's annual naval vessel construction plan under section 231. "Production readiness review" means a formal check, before construction starts, of whether the design is ready, engineering problems are solved, and the producer has planned adequately for production.
the actual law source: uscode.house.gov ↗public domain
(a)In General.—

The Secretary of the Navy may not approve the start of construction of the first ship for any major shipbuilding program until a period of 15 days has elapsed following the date on which the Secretary—

(1)

submits a report to the congressional defense committees on the results of any production readiness review;

(2)

certifies to the congressional defense committees that the findings of any such review support the start of construction; and

(3)

certifies to the congressional defense committees that at least 95 percent of all the basic and functional design drawing packages for the ship have reached final approval.

(b)Report.—

The report required by subsection (a)(1) shall include each of the following:

(1)

An identification of the degree to which detail design and production design drawings and related documents have been completed in accordance with the shipbuilding contract.

(2)

An assessment of the readiness of the shipyard facilities and workforce to begin construction.

(3)

The Navy’s estimated delivery date and a description of any risks that could affect such delivery date.

(4)

An assessment of the extent to which adequate processes and metrics are in place to measure and manage program risks.

(5)

With respect to the first ship, a description of the plans of the Navy to oversee and document the construction of the ship to ensure that the detail design supports the construction schedule for the ship.

(6)

A definition of the term “start of construction” that—

(A)

is applicable to the first ship; and

(B)

does not mean a point in time—

(i)

after the completion of 5 percent of lightship displacement; or

(ii)

after the advance procurement or advance construction of the ship.

(7)

An identification of any fabrication of the hull and superstructure of the ship that will occur before the date on which the Secretary submits the certifications required under paragraphs (2) and (3) of subsection (a).

(8)

An identification of the extent of to which vendor- and government-furnished information supports the overall maturity and stability of the ship’s design, including information regarding—

(A)

whether vendor selection is complete for major distributive systems and key equipment supporting operational requirements;

(B)

whether specifications are finalized for major distributive systems and key equipment; and

(C)

the status of factory acceptance testing, as applicable, to validate finalized specifications for major distributive systems and key equipment through manufacturing.

(c)Definitions.—

For the purposes of subsection (a):

(1)Basic and functional design.—

The term “basic and functional design”, when used with respect to a vessel, means design through computer aided models, and when used with respect to manned surface and undersea combatants, means design through the completion of three-dimensional computer aided modeling, that—

(A)

supports the major hull structure of the vessel;

(B)

sets the hydrodynamics of the vessel; and

(C)

positions and routes all major distributive systems of the ship, including electricity, water, and other utilities.

(2)First ship.—

The term “first ship” applies to a ship if—

(A)

the ship is the first ship to be constructed under that shipbuilding program; or

(B)

the shipyard at which the ship is to be constructed has not previously started construction on a ship under that shipbuilding program.

(3)Major shipbuilding program.—

The term “major shipbuilding program” means a program for the construction of combatant and support vessels required for the naval vessel force, as reported within the annual naval vessel construction plan required by section 231 of this title.

(4)Production readiness review.—

The term “production readiness review” means a formal examination of a program prior to the start of construction to determine if the design is ready for production, production engineering problems have been resolved, and the producer has accomplished adequate planning for the production phase.

Source credit: (Added Pub. L. 117–81, div. A, title X, § 1013(a), Dec. 27, 2021, 135 Stat. 1892; amended Pub. L. 118–159, div. A, title X, § 1024, Dec. 23, 2024, 138 Stat. 2053.)

history & why it existsrecord from the source credit
  • 2021Enacted · Pub. L. 117-81 · 135 Stat. 1892
  • 2024Amended · Pub. L. 118-159 · 138 Stat. 2053

A history note hasn’t been published yet. The record shows enactment by Pub. L. 117-81 on 2021-12-27.