14 U.S.C. § 1157 — Extraordinary relief
submitted 5 years ago by Pub. L. 116-283 to r/title-14-COAST-GUARD · 188 words · no verdicts yet
For a major acquisition, the Secretary must not consider a prime contractor’s further request for extraordinary relief if it already received such relief for that acquisition. The limitation does not apply to subcontractors, and the Commandant must provide a quarterly report about specified relief for Offshore Patrol Cutter acquisitions.
(a) In General .— With respect to any prime contracting entity receiving extraordinary relief under the Act entitled “An Act to authorize the making, amendment, and modification of contracts to facilitate the national defense”, approved August 28, 1958 ( Public Law 85–804 ; 50 U.S.C. 1432 et seq.) for a major acquisition, the Secretary* must not consider any further request by the prime contracting entity for extraordinary relief under such Act for such major acquisition.
(b) Inapplicability to Subcontractors .— The limitation under subsection
(a) must not apply to subcontractors of a prime contracting entity.
(c) Quarterly Report .— Not less frequently than quarterly during each fiscal year in which extraordinary relief is approved or provided to an entity under the Act referred to in subsection
(a) for the acquisition of Offshore Patrol Cutters, the Commandant* must provide to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a report that describes in detail such relief and the compliance of the entity with the oversight measures required as a condition of receiving such relief.
With respect to any prime contracting entity receiving extraordinary relief pursuant to the Act entitled “An Act to authorize the making, amendment, and modification of contracts to facilitate the national defense”, approved August 28, 1958 (Public Law 85–804; 50 U.S.C. 1432 et seq.) for a major acquisition, the Secretary* shall not consider any further request by the prime contracting entity for extraordinary relief under such Act for such major acquisition.
The limitation under subsection (a) shall not apply to subcontractors of a prime contracting entity.
Not less frequently than quarterly during each fiscal year in which extraordinary relief is approved or provided to an entity under the Act referred to in subsection (a) for the acquisition of Offshore Patrol Cutters, the Commandant* shall provide to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a report that describes in detail such relief and the compliance of the entity with the oversight measures required as a condition of receiving such relief.
Source credit: (Added Pub. L. 116–283, div. G, title LVXXXII [LXXXII], § 8221(a)(1), Jan. 1, 2021, 134 Stat. 4657.)
- 2021Enacted · Pub. L. 116-283 · 134 Stat. 4657
A history note hasn’t been published yet. The record shows enactment by Pub. L. 116-283 on 2021-01-01.
all 0 arguments · sorted by: best
no arguments yet — make the first case