42 U.S.C. § 16025Project timelines and authorization of appropriations

submitted 21 years ago by Pub. L. 109-58 to r/title-42-THE-PUBLIC-HEALTH-AND-WELFARE · 264 words · no verdicts yet

in plain englishAI-generated · not legal advice

By September 30, 2011, the Energy Secretary must pick the hydrogen production technology and design, or report an alternate date to Congress. Construction must finish by September 30, 2021, unless Congress gets an alternate date. Congress may spend up to $1.25 billion through 2015 and more after that.

(a) Target date to complete the first project phase: By September 30, 2011, the Secretary must (1) select the high-temperature hydrogen production technology and the prototype plant's initial design, or (2) send Congress a report setting a different target date. (b) Design competition for second project phase: (1) Through Idaho National Laboratory, the Secretary must fund up to 4 teams, for up to 2 years, to develop detailed competing proposals for the prototype reactor's final design, then pick one. (2) The Secretary may have the lead industrial partner of the winning design manage the systems integration for final design and construction. (c) Target date to complete project construction: By September 30, 2021, the Secretary must (1) finish building and start running the prototype reactor and its energy or hydrogen facilities, or (2) send Congress a report setting a different target date. (d) Authorization of appropriations: Congress may appropriate, for research and construction under this part (including transfers to the Commission for section 16024 work), (1) $1,250,000,000 for fiscal years 2006 through 2015, and (2) whatever sums are needed for each fiscal year from 2016 through 2021.
the actual law source: uscode.house.gov ↗public domain
(a) Target date to complete the first project phase

Not later than September 30, 2011, the Secretary shall—

(1)

select the technology to be used by the Project for high-temperature hydrogen production and the initial design parameters for the prototype nuclear plant; or

(2)

submit to Congress a report establishing an alternative date for making the selection.

(b) Design competition for second project phase
(1) In general

The Secretary, acting through the Idaho National Laboratory, shall fund not more than 4 teams for not more than 2 years to develop detailed proposals for competitive evaluation and selection of a single proposal for a final design of the prototype nuclear reactor.

(2) Systems integration

The Secretary may structure Project activities in the second project phase to use the lead industrial partner of the competitively selected design under paragraph (1) in a systems integration role for final design and construction of the Project.

(c) Target date to complete project construction

Not later than September 30, 2021, the Secretary shall—

(1)

complete construction and begin operations of the prototype nuclear reactor and associated energy or hydrogen facilities; or

(2)

submit to Congress a report establishing an alternative date for completion.

(d) Authorization of appropriations

There is authorized to be appropriated to the Secretary for research and construction activities under this part (including for transfer to the Nuclear Regulatory Commission for activities under section 16024 of this title as appropriate)—

(1)

$1,250,000,000 for the period of fiscal years 2006 through 2015; and

(2)

such sums as are necessary for each of fiscal years 2016 through 2021.

Source credit: (Pub. L. 109–58, title VI, § 645, Aug. 8, 2005, 119 Stat. 798.)

history & why it existsrecord from the source credit
  • 2005Enacted · Pub. L. 109-58 · 119 Stat. 798

A history note hasn’t been published yet. The record shows enactment by Pub. L. 109-58 on 2005-08-08.

all 0 arguments · sorted by: best

0/280

no arguments yet — make the first case