51 U.S.C. § 30307 — Requirement for independent cost analysis
submitted 16 years ago by Pub. L. 111-314 to r/title-51-NATIONAL-AND-COMMERCIAL-SPACE-PROGRAMS · 138 words · no verdicts yet
A translation hasn’t been published for this section yet. The official text below is complete and authoritative.
In this section, the term “implementation” means all activity in the life cycle of a project after preliminary design, independent assessment of the preliminary design, and approval to proceed into implementation, including critical design, development, certification, launch, operations, disposal of assets, and, for technology programs, development, testing, analysis, and communication of the results.
Before any funds may be obligated for implementation of a project that is projected to cost more than $250,000,000 in total project costs, the Administrator* shall conduct and consider an independent life-cycle cost analysis of the project and shall report the results to Congress. In developing cost accounting and reporting standards for carrying out this section, the Administrator shall, to the extent practicable and consistent with other laws, solicit the advice of experts outside of the Administration*.
Source credit: (Pub. L. 111–314, § 3, Dec. 18, 2010, 124 Stat. 3365.)
- 2010Enacted · Pub. L. 111-314 · 124 Stat. 3365
A history note hasn’t been published yet. The record shows enactment by Pub. L. 111-314 on 2010-12-18.