33 U.S.C. § 598c — Easements for hurricane and storm damage reduction projects
submitted 1 year ago by Pub. L. 118-272 to r/title-33-NAVIGATION-AND-NAVIGABLE-WATERS · 658 words · no verdicts yet
This section lets certain hurricane and storm projects use a nonperpetual easement when the Secretary gives the required certification and warning. It also requires disclosure of perpetual-easement requirements and lists projects covered by a two-year implementation rule.
(a) For a hurricane and storm damage-reduction project requiring a perpetual easement, the Secretary must, when the non-Federal sponsor asks, certify real-estate availability and build with a nonperpetual easement if the certification and construction comply with the Chief of Engineers’ report and project partnership agreement. The Secretary must warn that if the easement expires and is not extended, the Secretary cannot perform the Federal responsibility, required nourishment, repair or rehabilitation under section 701n, or other relevant Federal assistance. (b) For projects or modifications authorized after January 4, 2025, that require a perpetual easement for Federal participation, the Chief of Engineers’ report must disclose that requirement. (c) As far as practicable, the Secretary must identify and accept the minimum interests needed, under section 598b. (d) During the 2 years beginning January 4, 2025, each covered project must be carried out consistently with its completed initial construction and periodic nourishment, including repair and restoration, despite the cited 1995 Corps memorandum. Covered projects are the Florida projects listed in subparagraphs (A) through (BB), including the named reaches, segments, counties, beaches, keys, and islands. Congress expresses the view that an easement for constructing and maintaining such a project should last at least 50 years but no longer than the project’s life. (e) This section does not change section 2213(d).
With respect to a project for hurricane and storm damage reduction for which the Secretary is requiring a perpetual easement, the Secretary shall, upon request by the non-Federal interest for the project, certify real estate availability and proceed to construction of such project with a nonperpetual easement if—
such certification and construction are in compliance with the terms of the report of the Chief of Engineers for the project and the applicable project partnership agreement; and
the Secretary provides the non-Federal interest with formal notice that, in the event in which the nonperpetual easement expires and is not extended, the Secretary will be unable to—
fulfill the Federal responsibility with respect to the project or carry out any required nourishment of the project under the existing project authorization;
carry out repair and rehabilitation of the project under section 701n of this title; and
provide any other relevant Federal assistance with respect to the project.
For any project for hurricane storm damage risk reduction, or a proposal to modify such a project, that is authorized after January 4, 2025, for which a perpetual easement is required for Federal participation in the project, the Secretary shall include in the report of the Chief of Engineers for the project a disclosure of such requirement.
To the maximum extent practicable, the Secretary shall, at the request of the non-Federal interest for a project for hurricane storm damage risk reduction, identify and accept the minimum real estate interests necessary to carry out the project, in accordance with section 598b of this title.
During the 2-year period beginning on January 4, 2025, notwithstanding any requirement of the Secretary for a covered project to comply with the memorandum of the Corps of Engineers entitled “Standard Estates – Perpetual Beach Nourishment and Perpetual Restrictive Dune Easement” and dated August 4, 1995, the Secretary shall carry out each covered project in a manner consistent with the previously completed initial construction and periodic nourishments of the project, including repair and restoration work on the project under section 701n(a) of this title.
In this subsection, the term “covered project” means an authorized project for hurricane and storm damage reduction in any one of the following locations:
Brevard County, Canaveral Harbor, Florida – Mid Reach.
Brevard County, Canaveral Harbor, Florida – North Reach.
Brevard County, Canaveral Harbor, Florida – South Reach.
Broward County, Florida – Segment II.
Broward County, Florida – Segment III.
Dade County, Florida – Main Segment.
Dade County, Florida – Sunny Isles Segment.
Duval County, Florida.
Fort Pierce Beach, Florida.
Lee County, Florida – Captiva.
Lee County, Florida – Gasparilla.
Manatee County, Florida.
Martin County, Florida.
Nassau County, Florida.
Palm Beach County, Florida – Jupiter/Carlin Segment.
Palm Beach County, Florida – Delray Segment.
Palm Beach County, Florida – Mid Town.
Palm Beach County, Florida – North Boca.
Palm Beach County, Florida – Ocean Ridge.
Panama City Beaches, Florida.
Pinellas County, Florida – Long Key.
Pinellas County, Florida – Sand Key Segment.
Pinellas County, Florida –Treasure Island.
Sarasota, Lido Key, Florida.
Sarasota County, Florida – Venice Beach.
St. Johns County, Florida – St. Augustine Beach.
St. Johns County, Florida – Vilano Segment.
St. Lucie County, Florida – Hutchinson Island.
It is the sense of Congress that, for the purpose of constructing and maintaining a project for hurricane and storm damage risk reduction, the minimum estate necessary for easements may not exceed the life of the project nor be less than 50 years.
Nothing in this section may be construed to affect the requirements of section 2213(d) of this title.
Source credit: (Pub. L. 118–272, div. A, title I, § 1145, Jan. 4, 2025, 138 Stat. 3035.)
- 2025Enacted · Pub. L. 118-272 · 138 Stat. 3035
A history note hasn’t been published yet. The record shows enactment by Pub. L. 118-272 on 2025-01-04.
all 0 arguments · sorted by: best
no arguments yet — make the first case